CIVIL ENGINEERING WING

The Civil Engineering Cell of the Department attached to the Directorate functions under 1(one) Executive Engineer, 1(One) Sub-Divisional Officer and 2(Two) Junior Engineer which looks after construction, repair and maintenance of both functional and residential buildings of the Department.

The Department has taken up infrastructure development and the status of the ongoing projects are as below:

Completed project during 2024-25

Sl

Name of project

Date of completion

1

Construction of Heliport at Chumoukedima

May. 2024

2

Construction of Helipad at Pughoboto

September. 2024

3

Construction of Helipad at Chen

June. 2024

4

Construction of Helipad at Yaongyimsen

July. 2024

 

 

 

Ongoing projects during 2024-25

Sl

Name of project

Progress in %

I

Under State Plan

1

Construction of Helipad at Suruhoto

90%

2

Construction of Helipad at Satakha

40%

3

Construction of Helipad at Phek

65%

4

Construction of Sub-station and garage at Mangkolemba

10%

5

Construction of Sub-station and garage at Tseminyu

15%

6

Construction of Sub-station and garage at Pfutsero

10%

7

Construction of Sub-station and garage at Meluri

10%

8

Construction of New Station building at Zunheboto

10%

 

II

Under CSS

1

Construction of Interstate Bus & Truck Terminus at Tuensang

85%

2

Conversion of NST Central workshop to bus station, night parking and marketing complex at Dimapur

40%